As-Built Survey Drawings in Vancouver Island: A Guide for Civil Infrastructure

When a civil project on Vancouver Island is finished, the design drawings no longer tell the whole story. Pipes are shifted to clear an existing service, a manhole ends up a little lower than planned, a curb return is adjusted on site. An as-built survey measures what was actually built, so the owner, the engineer and the municipality have a record they can trust for decades.

This page explains what an as-built survey captures, when each part has to be measured, how the drawings are prepared, and how Site Wiz has handled as-builts on recent projects in Langford and Colwood.

Key Takeaways

  • An as-built survey records the final position and elevation of pipes, structures, services and surfaces.
  • Underground work has to be measured while the trench is open; once it is backfilled, the chance is gone.
  • As-builts are tied to the same control used for layout, so they can be compared directly with the design.
  • Differences from the design are noted on the drawing so the engineer of record can prepare the record drawings.
  • Site Wiz has carried out as-built surveys throughout construction on major projects in Langford and Colwood.

What an As-Built Survey Captures

On a typical road, subdivision or site servicing project, the as-built survey covers:

  • Storm and sanitary sewers: pipe ends, bends and fittings, manhole and catch basin locations, rims and inverts.
  • Water and other services: valves, hydrants, tees, bends, service connections and their ends at the property line.
  • Shallow utilities: ducts, pedestals, kiosks and poles installed as part of the work.
  • Surfaces: curbs, sidewalks, pavement edges and final grades.
  • Existing utilities found during construction: lines exposed in the trench that were not shown, or not shown correctly, on the drawings.

Each item is measured for position and elevation, then compared with the design. For a closer look at the drawing side, see our guide to as-built record drawings in BC.

Timing: Measure Before It Is Buried

An as-built survey is not one visit at the end of the project. Most of the important information is underground, so it has to be picked up while it is still visible:

  • Pipes and fittings: before backfill, as each run is laid.
  • Structures: when manholes and catch basins are set, and again when rims are adjusted to final grade.
  • Gravels and subgrade: where the contract requires grade checks before paving.
  • Final surfaces: curbs, pavement and finished grades at the end of the job.

Coordinating these visits with the pipe crew is the key to a complete record. A missed fitting can mean digging it up again later.

As-built survey timeline on Vancouver Island: when to measure pipes, structures, gravels and final surfaces

How As-Built Drawings Are Prepared

  1. Same control as layout. As-builts are measured from the site control used to stake the work, so the record and the design use one reference. See our guide to the construction survey control network.
  2. Field measurement. GNSS and total stations, depending on the site, with checks on known points.
  3. Comparison with design. Measured positions and elevations are compared with the issued-for-construction drawings.
  4. Drawing and data. Differences are noted on the drawing, and the data is delivered as CAD files, PDFs and point files in the format the engineer specifies.

Office-based work, including record drawings prepared from your own field data, is also available to contractors anywhere in Canada through our remote services.

As-Builts and Municipal Close-Out

Municipalities on Vancouver Island generally require record drawings before they accept new roads and utilities. Each one sets its own standards for content, format and digital files, usually in its engineering specifications or subdivision bylaw. The engineer of record normally prepares and signs the record drawings; the as-built survey provides the measured data behind them.

Before the project starts, check which standard applies and what the engineer needs from the survey. Agreeing the deliverables early avoids repeat site visits at close-out.

Project Examples on Vancouver Island

Site Wiz has worked with Scansa on major infrastructure projects on the West Shore:

Millstream and Bear Mountain Parkway, Langford

A project that took more than 15 months to complete. Site Wiz was responsible for all field layout, volume calculations and as-built surveys throughout construction.

Olympic View Traffic Circle, Colwood

A 12-month-plus infrastructure project. Site Wiz has been responsible for all field layout, volume calculations and as-built surveys on the project.

More of our work is on our projects page. Because the same team handled layout and as-builts on these projects, the record was measured from the same control that was used to build the work. Read more about construction layout in Victoria.

Planning a project on Vancouver Island? Contact Site Wiz with your drawings and schedule, and we will plan the as-built visits around your crews.

Frequently Asked Questions

What is the difference between an as-built survey and record drawings?

The as-built survey is the measurement of what was built. Record drawings are the final drawings that show it, usually prepared by the engineer of record using the survey data.

When should as-built surveys be booked?

At the start of the project. Underground work has to be measured before backfill, so the visits need to follow the construction schedule.

Which areas do you cover?

Our field team is based in Victoria and works across Greater Victoria, including Langford and Colwood, on Vancouver Island and on projects across BC.

Is an as-built survey a legal survey?

No. As-built surveys record construction. Legal and property boundary surveys in BC are completed by a BC Land Surveyor.